Floor Handover Inspection Checklist

Floor handover inspection checklist

Final payment is the owner's last contractual lever. Once 100% is released, the warranty triangle becomes a customer-service conversation, not a contract. This checklist is the 35-item inspection that should happen before the last 10% is released. Five inspection categories — visual, dimensional, documentation, performance, snag-list — each with named questions and named pass/fail criteria. Run the inspection with the applicator present, capture photos at named locations, and trigger re-work at applicator cost for any failed item before payment is released.

Category 1 of 5 — Visual

Visual inspection (8 items)

Walk the floor at a slow walking pace under representative lighting. Side-light reveals defects that flat overhead light hides.

1. Surface uniformity — colour and texture
No visible streaking, no colour boundary lines between pour bays, no aggregate-density variation. Pass: uniform appearance across full project area. Fail: visible boundary lines between pour bays trigger re-work.
2. No fish-eyes / pinholes / craters
Inspect under side-light from a low angle. Pass: zero visible craters under side-light. Fail: any craters at named grid locations require spot-repair before sign-off.
3. No trowel marks / roller marks at corners
Corners and column intrusions are the highest-risk zone for finish quality. Pass: trowel marks invisible at standing-eye level under representative lighting.
4. Edge detail — perimeter wall transition
Clean termination at wall meet, integral cove where specified. Pass: no gaps, no raised edges, cove radius matches spec.
5. Column + drain detail
Column intrusions and floor drains have clean radius detail per design. Pass: resin fully wraps detail, no gaps, drain flange flush or below floor plane.
6. Joint sealant — visible quality
Joint sealant flush with surface or slightly recessed, no shoulder lift, no air bubbles. Pass: uniform finish across full joint length.
7. Gloss / sheen uniformity
Matte / satin / gloss finish uniform across project area. Pass: visual sheen uniformity at standing-eye level.
8. Embedded debris / aggregate exposure consistency
Broadcast aggregate uniformly exposed in topcoat; no clusters of bare resin between aggregate. Pass: uniform aggregate distribution across full area.
Category 2 of 5 — Dimensional

Dimensional verification (5 items)

Measure with calibrated tools. Photo each measurement at the named grid location.

9. Thickness verification — minimum 5 grid points per 100 m²
Depth gauge measurement at named grid points. Pass: all measurements within ± 0.5 mm of spec. Fail: below-spec zones flagged for re-pour.
10. Flatness — straight-edge across 3 m
3 m straight-edge across multiple orientations. Pass: ≤ 3 mm deviation under straight-edge over 3 m for self-levelling systems.
11. Cove height + radius
100 mm cove height, 30 mm radius template fit. Pass: integral cove matches spec at all locations.
12. Joint width + depth
Joint width per spec (8 / 12 / 20 mm), depth-to-width ratio 2:1. Pass: measured joint dimensions match joint plan.
13. Floor levels match transition strips
Floor finish level matches adjacent flooring at threshold transitions. Pass: level mismatch ≤ 2 mm at transition strip locations.
Category 3 of 5 — Documentation

Documentation handover (10 items)

Five documents minimum, ten if the project is regulatory-sensitive. All in the project file before any payment is released.

14. Manufacturer product warranty certificate
Registered to project address, SKU + lot listed, term + scope explicit. See warranty types.
15. Applicator installation warranty
Term + scope + applicator certification number + signed by company principal.
16. ICRI CSP measurement records
CSP measurement chart at minimum 3 locations per 1,000 m² with photos. See ICRI CSP guide.
17. ASTM F2170 moisture log
In-situ moisture probe results at named depths + locations.
18. Pull-off test report (independent lab)
EN 1542 / ASTM D7234 results at 6+ locations with failure mode + photos + ISO 17025 lab signature. See pull-off guide.
19. Slip-class test report
DIN 51130 / EN 16165 PTV results at named zones, independent lab signature. See slip class explained.
20. Fire reaction certificate
EN 13501-1 classification certificate from notified body.
21. HACCP / antimicrobial certificate (if food zone)
ISO 22196 + food-contact safety certificates if applicable to use case.
22. Completion certificate
Pour dates, system build-up layer-by-layer with SKU + thickness, final inspection sign-off.
23. Maintenance protocol
Single-page maintenance card for facility manager. See care by system type.
Category 4 of 5 — Performance

Performance verification (5 items)

The performance tests already happened in Phase 7 of the project timeline. At handover, verify the test reports are in hand and meet thresholds.

24. Pull-off test result above threshold
≥ 1.5 MPa for heavy-duty industrial, ≥ 1.0 MPa for thin systems, with Mode C cohesive failure. Pass: all locations above threshold. Fail: below-threshold zones require re-pour.
25. Slip class achieved per zone
R-class or PTV result matches tender spec per named zone. Fail: below-target zones require re-broadcast.
26. Adhesion at perimeter cove + column detail
Visual + tap test for hollow zones at perimeter + columns. Pass: no hollow zones detected by tap test.
27. Joint sealant adhesion test
Manual pull test at sample joints to verify sealant cohesion. Pass: sealant cohesive failure (sealant tears), not adhesive failure (peels from joint shoulder).
28. Cleaning protocol test
Run the daily cleaning protocol per maintenance card on a sample area. Pass: floor cleans to handover finish with specified chemistry.
Category 5 of 5 — Snag list

Snag list + sign-off (7 items)

The snag list captures items that pass visual but aren't quite right — minor surface marks, edge defects under 5 mm, sealant fills at column-to-floor junctions. Capture, photograph, agree resolution before sign-off.

29. Photograph every defect at named location
Each snag item photographed with location grid reference. Document is owner's contractual evidence.
30. Resolution per snag — repair vs accept
For each item: applicator repair OR owner accepts as-is. Each decision documented and signed.
31. Snag list deadline before final payment
Repair items have deadline (typically 14 days post-handover). Final payment released only after all items closed or formally accepted.
32. Hand-over of unused material
Spare material for future repair (typically 5-10 kg resin + matching SKU) handed over with labels.
33. Pour date + cure schedule documented
When traffic restrictions lift (light traffic, full chemical resistance, etc.). Schedule in handover doc.
34. Applicator emergency contact + lifecycle re-visit
Named contact + scheduled annual inspection (free) + year-1 spot-repair allowance.
35. Final sign-off document
Owner + applicator signatures on handover summary + snag-list resolution + payment release authorisation.

Inspection logistics

  • Inspector: owner representative + applicator project manager + (recommended) independent consultant.
  • Equipment: 3 m straight-edge, depth gauge, light source (side-light), ICRI CSP comparator chips (for record verification), tap-test hammer, smartphone camera.
  • Lighting: representative use-case lighting + supplementary side-light for surface inspection.
  • Timing: after full system cure (typically day 7+), before owner occupation, before final payment.
  • Duration: 2–4 hours for 500 m², plus document review.
  • Documentation: photographs at named locations + signed inspection record + snag list. All in project file.

What to do if items fail

  • Visual defect: Applicator repair at applicator cost. Re-inspect after repair.
  • Dimensional below spec: Re-pour the affected zone at applicator cost.
  • Documentation missing: Withhold final 10% until document delivered. Set 30-day deadline.
  • Performance below threshold: Re-broadcast (slip) or re-pour (pull-off) the affected zone at applicator cost.
  • Snag-list dispute: Independent consultant inspection. Cost shared depending on outcome.

Final read

Thirty-five items, five categories, one signed document. The inspection is the last contractual lever for the owner and the most predictive event for floor lifecycle. Run it with discipline; refuse to release final payment until all categories pass. The applicator who delivers a floor that passes a 35-item inspection has a 15-year floor on his hands. The owner who skips the inspection has a year-two warranty fight. Related: procurement timeline · warranty types · BOQ template · evaluate a floor installer · compliance verification.

Sources

  • Sikafloor handover guidelines.
  • Mapei Mapefloor handover guidelines.
  • EN 13813 — Synthetic resin screeds quality standards.
  • EN 1542 / ASTM D7234 pull-off testing standards.
  • DIN 51130 + EN 16165 PTV slip-resistance standards.
  • IL contractor handover documentation — 30+ resin floor projects.
  • Floor.DSGN IL inspection record documentation.